Main civils work and Euston station job behind hike on project

The minister responsible for HS2 has raised concerns about the rate at which costs on the project are growing.

In his six month report to parliament yesterday, Andrew Stephenson said HS2 had used up an additional 拢500m of its 拢5.6bn contingency fund since his last update.

He said: 鈥淗S2 Ltd has drawn 拢1.3bn of its 拢5.6bn delegated contingency, meaning 拢4.3bn remains. Contingency drawn to date reflects an increase of 拢500m.

鈥淗S2 is reporting 拢1.7bn of potential future cost pressures that are currently presenting across the programme. This reflects an increase in potential further cost pressures of 拢400m since my last update.鈥�

BBVS Old Oak Common HS2 site handover

Source: HS2 Ltd

Worries about rising costs at Euston station and on some of the main civils works have been flagged by the minister in charge of the HS2 project

He said this meant in the past six months the combined increase in actual and potential additional costs was 拢900m.

Stephenson added: 鈥淲hile these pressures are manageable within the target cost given the remaining contingency, I am nonetheless concerned at the rate of their increase. I expect HS2 to maintain its focus on delivery to the target cost.鈥�

The update also revealed where the additional costs might be.

It includes an estimate of 拢800m for extra civils costs, stemming from additional design costs and slower than expected progress in some areas. This increase is 拢200m more than the figure forecast in October.

It also includes a potential 拢400m more being spent on the HS2 station at Euston.

Stephenson said: 鈥淭he move to a smaller, less complex 10-platform single-stage delivery strategy at Euston is now the basis for ongoing design work and other activities.

鈥淭he department anticipates that this will assist in addressing the cost pressure at Euston.鈥�

Other potential cost hikes include 拢200m for changes to Network Rail infrastructure at Euston and Old Oak Common as well as a further 拢300m in aggregate costs across the whole scheme.