Work set to take two years to complete
The government has given an update on plans to dismantle the Grenfell tower in west London.
The work is due to be carried out by demolition contractor Deconstruct which has been on site since 2017, having carried an assortment of jobs including clearance and safety monitoring.
In the update, the government said a crane will be erected at the site later this summer with more scaffolding going up as part of the work.
It added: “We will sensitively remove, preserve and safely store the architectural crown and the elements of the Tower agreed with the community as we carefully take the building down.”
The update said some of the materials from the tower will be used as part of a planned Grenfell memorial nearby.
And it said it was “exploring different ways to illuminate the Tower” during the work and said the banner with the green heart design will be moved down the building in stages as the tower come down.
The government has previously said it had awarded Deconstruct the £12.25m contract without competition because “any change in contractor would cause significant inconvenience and substantial duplication of costs”.
The job is expected to take two years to complete.
No comments yet