ΞΆΓάΘ¦

Read our policy.

Cost breakdown of the Paddington Health Campus
Capital costs summaryCosts exc VAT (Β£000s)VAT (Β£000s)Costs inc VAT (Β£000s)
Departmental costs187,41232,797220,209
On costs339,20959,362398,571
Works cost total526,62192,159618,780
Provisional location adjustment121,12321,197142,320
Fees58,297Μύ58,297
Non-works costs17,6463,08820,734
Planning contingency65,13211,39876,530
Total (for approval purposes)788,819127,842916,661
Inflation adjustments164,09828,717192,815
Forecast for total out-turn cost952,917156,5591,109,476